40 FSERs built in 4 years.
5 Modular builds to date.
1.5 to 2 Year FSER project schedule.
CHALLENGE
HCA wanted to expand its Free-Standing Emergency Room (FSER) program and needed a partner who understood the healthcare industry. HCA chose Sevan to act as their owner’s representative to handle all FSER site builds across the country.
SOLUTION
Sevan managed contractors and other third parties to complete all site work. Each project was broken up into four project stages which included:- Real estate, budgeting and design
- Permitting, utilities and preconstruction
- Construction
- Closeouts
RESULTS
Since 2017, Sevan has completed 40 FSERs for HCA, including five modular builds. Sevan also optimized the project schedule, so each FSER is completed in 1.5-2 years depending on the site requirements and state/municipality regulations.